Installation process of organic fertilizer production line equipment

Tongda Heavy Industry is a professional fertilizer equipment manufacturer with more than 20 years of production experience. Today, I will mainly tell you about the installation process of organic fertilizer production equipment:

  1. Before installation, check whether the dimensions of each installation foundation meet the requirements of the drawings according to the plan and foundation plan of the organic fertilizer production equipment. If there is any discrepancy, it should be repaired until the dimensions are correct before installation.
  2. The installer should first be familiar with the installation requirements of each organic fertilizer production equipment and carry out construction in strict accordance with the technical requirements.
  3. The organic fertilizer production equipment may be deformed, damaged or lost during transportation. Therefore, before installation, it is necessary to check and accept the equipment list, and take corresponding measures to make the equipment in good condition before installation.
  4. Before entering the installation site, each organic fertilizer production equipment should be numbered, and the installation process card and schedule should be formulated. According to the requirements of the installation process sequence, the equipment should be transferred to the site for installation one by one.
  5. Installation sequence: from top to bottom, first install the host equipment and rack, and then install the connecting pipes and electrical equipment.
  6. Tools required for installation: equipment and materials must be available.
  7. After installation, each rotating part of the organic fertilizer production equipment must rotate flexibly, without jamming and impact sound, and each connecting part must be firm and sealed, and there must be no powder leakage, air leakage, oil leakage and other phenomena.
  8. The installation of electrical equipment should comply with relevant regulations, the direction of each line should be clear, and there should be no leakage or leakage of electricity. Wires and cables should have protective casings to prevent mice from being bitten.
  9. After all the equipment is installed, each single machine should be tested with empty car, and it can be put into load test after normal operation.
  10. Before the load test, calibrate the electronic batching scale and packing scale, and require the specified accuracy.
  11. The load can be operated for 8 hours, and the production and use can be started after there is no fault.