Installation process of organic fertilizer production line equipment

  1. Before installation, check whether the dimensions of each installation foundation meet the drawing requirements according to the organic fertilizer production equipment plan and foundation diagram. If there are any discrepancies, repairs should be carried out until the dimensions are correct before installation.
  2. The installation personnel should first be familiar with the installation requirements of each organic fertilizer production equipment and carry out construction in strict accordance with the technical requirements.
  3. Organic fertilizer production equipment may be deformed, damaged or lost during transportation. Therefore, before installation, check and accept the equipment detailed list, and take corresponding measures to ensure that each equipment is in good condition before installation.
  4. Each organic fertilizer production equipment should be numbered before entering the installation site, and the installation process flow card and schedule should be formulated. According to the installation process sequence requirements, the equipment should be transferred to the site one by one for installation.
  5. Installation sequence: from top to bottom, first install the host equipment and rack, and then install the connecting pipes and electrical equipment.
  6. Tools required for installation: equipment and materials must be available.
  7. After installation, each rotating part of the organic fertilizer production equipment must rotate flexibly without jamming, bumping or impacting sounds. Each connecting part must be firm and sealed, and there must be no powder leakage, air leakage, oil leakage, etc.
  8. The installation of electrical equipment should comply with relevant regulations. The direction of each line should be clear, and there should be no electricity leakage or leakage. Wires and cables should have protective shells to prevent them from being chewed by mice.
  9. After all equipment is installed, each single machine should be put into empty test operation. Only when the operation is normal can it be put into load test operation.
  10. Before load test, the electronic batching scale and packaging scale should be calibrated to meet the specified accuracy.
  11. After running under load for 8 hours, it can be handed over to the factory for production use if there are no faults.