How to install organic fertilizer processing equipment after purchasing?

How to install the organic fertilizer processing equipment after purchasing? Tongda Heavy Industry is a professional fertilizer equipment manufacturer with many years of production experience. Today I will tell you about the installation process of organic fertilizer production equipment.
On-site process and steps of organic fertilizer production line installation:
1. Before installation, check whether the dimensions of each installation foundation meet the requirements of the drawing according to the plan and foundation diagram of the organic fertilizer production equipment. If there is any discrepancy, it should be repaired until the dimensions are correct before installation.
2. The installation personnel should be familiar with the installation requirements of each organic fertilizer production equipment, and carry out construction in strict accordance with the technical requirements.
3. The organic fertilizer production equipment may be deformed, damaged or lost during transportation. Therefore, before installation, it is necessary to check and accept it against the equipment schedule, and take corresponding measures to ensure that the equipment is in good condition before installation.
4. Each organic fertilizer production equipment should be numbered before entering the installation site, and the installation process card and schedule should be formulated. According to the requirements of the installation process sequence, the equipment should be transferred to the site one by one for installation.
5. Installation sequence: from top to bottom, first install the host equipment and the rack, and then install the connecting pipes and electrical equipment.
6. Tools required for installation: organic fertilizer processing equipment and materials must be available.
7. After installation, each rotating part of the organic fertilizer production equipment must rotate flexibly without jamming or impacting sound.
8. The installation of electrical equipment should comply with relevant regulations. The direction of each line should be clear, and there should be no leakage or leakage. Wires and cables should have protective casings to prevent mice from biting.
9. After the installation of all the equipment is completed, each single machine should be tested with an empty car, and it can be put into a test run with a load when it is running normally.
10. Before the load test run, calibrate the electronic batching scale and packing scale to meet the specified accuracy.
11. After the load runs for 8 hours, it can be handed over to the factory for production and use after there is no fault.